Building Project Mile Stones:
- Apr 25, 2010 - Blessing of Pavilion and Playground
- Nov 25, 2009 - Activity Center and Playground
- Jan 03, 2007 - Dedication of Lower Level
- Apr 25, 2005 - Dedication of New Church
- Apr 04, 2005 - First Mass Celebrated in New Church
- Nov 21, 2004 - Open House Tours of Construction Progress
- Aug 24, 2004 - Structural Steel Topping-Out
- Jun 04, 2004 - Building Permit Issued
- Mar 21, 2004 - Ground Breaking Ceremony
- Dec 01, 2003 - Construction Dwgs (CD) Available
- Sep 12, 2003 - Scale Model Unveiled at Golf Tournament
- Aug 20, 2003 - Diocesan Worship Comittee Approval
- Jul 15, 2003 - DD Dwgs Presented to Diocese
- Feb 26, 2003 - Begin Design Development (DD) Phase
- Feb 14, 2003 - Schematic Design Approved by Bishop Sheridan
- Feb 14, 2003 - Financial Plan Approved by Bishop Sheridan
- Dec 11, 2002 - General Contractor Selected
- Nov 23, 2002 - First Fruits Weekend
- Nov 17, 2002 - Celebration Event/Commitment Weekend
- Oct 30, 2002 - Complete Home Gatherings
- Oct 18, 2002 - 24-Hour Prayer Vigil on Site
- Jul 27, 2002 - Begin Schematic Design Phase
- May 24, 2002 - Site Plan approved by Colo Springs Diocese
- Apr 24, 2002 - Decision to proceed with Site Plan E
- Apr 18, 2002 - Capital Feasibility Study Completed
- Feb 12, 2002 - Site Analysis Work Completed
- May 6, 2001 - Property Dedicated by Bishop Hanifen
- Apr 23, 2000 - First Mass Celebrated
|
|